Ontario Solitary Confinement Class Action, February 23, 2018
February 23, 2018
A timetable leading to the certification hearing in this matter has been set:
Remaining steps to be completed: | By which party: | Date to be completed by: |
Certification Motion Materials | Plaintiff | October 16, 2017 |
Responding Motion Materials | Defendant | February 15, 2018 |
Reply Motion Materials | Plaintiff | April 30, 2018 |
Cross-examinations, and any motions arising therefrom, to be completed by | July 2, 2018 | |
Certification Factum | Plaintiff | August 2, 2018 |
Responding Factum | Defendant | September 3, 2018 |
Reply Factum (if necessary) | Plaintiff | October 1, 2018 |
Return of the Motion (2 days) | November 13-14, 2018 |